Circular Line - Metro do Porto
Description
Client | Metro do Porto
Project duration | 44 months
The execution of the Circular Line of the Porto Metro involves a complex and multifaceted project that is subdivided into several main works.
Below is a detailed description of each of the main areas of work:
TUNNELS
1. Instrumentation of Surrounding Buildings and Infrastructures:
-
Monitoring and control of vibrations, displacements, and other influences on buildings and infrastructures near the excavation site.
2. Affected Services and Heritage Protection:
-
Identification and protection of public services (water, sewage, electricity, telecommunications) and historical heritage affected by the works.
3. Reinforcement and Protection Works for Buildings and Infrastructures:
-
Structural reinforcement and protective measures to ensure the integrity of buildings and infrastructures during tunnel construction.
4. NATM Excavation Fronts and Temporary Lining:
-
Use of the NATM (New Austrian Tunneling Method) for excavation, followed by the application of temporary lining for stabilization.
5. Final Lining:
-
Application of permanent lining after the completion of excavation to ensure the durability and safety of the tunnel.
STATIONS
-
Instrumentation of Surrounding Buildings and Infrastructures
-
Affected Services and Heritage
-
Protection Reinforcement and Protection Works for Buildings and Infrastructures
-
Excavation and Peripheral Containment:
-
Excavation of stations and implementation of containment measures for stabilization.
-
Excavation of stations and implementation of containment measures for stabilization.
5. Structures:
-
Construction of the main structures of the stations and their access points.
6. Water and Sewage Systems:
-
Implementation of potable water systems, sewage, wastewater, and rainwater systems, including pumping systems.
7. Finishes
Installation, Equipment, and Electrical Systems
INSTALLATION, EQUIPMENT, ELECTRICAL SYSTEMS, SIGNALING, AND TELECOMMUNICATIONS
1. Medium Voltage Power Supply and Substations:
-
Medium voltage power supply systems and substations.
2. Catenary:
-
Installation of the catenary system for the power supply of the carriages.
3. Intrusion Detection and Access Control:
-
Implementation of security systems for access control and intrusion detection.
4. Lighting and Low Voltage Power Supply, Fire Detection and Fighting:
-
Installation of lighting systems, low voltage power supply, and fire detection and fighting systems.
-
Implementation of railway signaling and telecommunications systems for the safe and efficient operation of the line.
RAILWAY
Concrete Track Platform, Multitubulars, Track Drainage, LVT Concrete Blocks, Vignole 60E6 Rail:
-
Construction of the railway infrastructure, including the concrete platform, drainage systems, installation of tracks, and specific concrete blocks for track support.
This comprehensive project is essential for the expansion and improvement of the public transportation network in Porto, contributing to more efficient and sustainable urban mobility.
Contact
Oporto
Lisbon
Rua Esteiro de Campanhã, 82
4300 - 174 Porto
Tel (+351) 220 434 870
Email: geral@diligentparallel.com
Av. Freedom, 69 - 4E
1250-140 Lisbon
Tel (+351) 210 539 633